TRC
R1 and R2 Briefs for ITRP
The International LC Accelerator Subgroup has requested a ~1 page
update on each of the R1 and R2 items identified in the TRC. The update should describe the latest
results as well as expected R&D before June 2004. The relevant R1 and R2 items are listed and this is followed by a
table of proposed authors for each of the items. The first author in the list has primary responsibility. The date for these pages is January 20th,
2004. We should have drafts of all
pages by January 15th, 2004 for a final edit. To accommodate this tight timescale please
plan to have drafts to the co-authors by Tuesday morning January 13th. Please include relevant references and links
to web documents. Figures can be
included in the brief or referenced in a web link.
R1
- For
JLC-X/NLC, the validation of the presently achieved performance (gradient
and trip rates) of low group velocity structures—but with an
acceptable average iris radius, dipole mode detuning and manifolds for
damping—constitutes the most critical Ranking 1 R&D issue. Tests
of structures with these features are foreseen in 2003.
- The other
critical element of the rf system is the dual-moded SLED-II pulse
compression system. Tests of its rf power and energy handling capability
at JLC-X/NLC design levels are planned in 2003. As far as the 75 MW X-band
PPM klystron is concerned, the Working Group considers the JLC-X PPM-2
klystron a proof of existence (although tested only at half the repetition
rate). A similar comment can be made regarding the solid-state modulator
tested at SLAC.
R2
- There
must be a full test of the JLC-X PPM klystron at the specified repetition
rate of 120 or 150 Hz.
- These
klystrons should be tested with the NLC modulator (at full specs and
including arcing tests) and form part of a linac subunit test. The latter
should also comprise the dual-moded SLED-II complete system, several
damped and detuned structures, installed in the accelerator environment
(with temperature control, for instance), and LLRF and controls systems.
The test should be made with beam. The present plan is to perform this
sort of test with a full girder of structures (some of them being detuned
and damped) in 2004.
- For all
the damping ring designs, further simulation studies are needed to understand
the magnitude of the electron cloud effects and to explore possible means
of suppressing these effects. Experiments in existing rings are needed to
test the electron cloud simulations. Possible cures for the electron cloud
(including chamber coatings, superimposed magnetic fields, and gaps in the
bunch pattern) need to be experimentally investigated.
- Further
simulations of the fast ion instability are also necessary. Experiments in
the ATF and other suitable rings are needed to test the predictions of
these simulations.
- Damping
ring extraction kicker stability, required at the level of <10-3, is an important issue.
Continued studies including experiments with the ATF double-kicker system
are needed.
- Finally,
additional simulations of emittance correction in the damping rings are
needed, including the effects listed in Section 7.2.3.2. Additional experiments
in the ATF and other operating rings are needed to test the emittance
correction algorithms.
- For all
low emittance transport designs, the static tuning studies, including
dynamic effects during correction, must be completed.
- The most
critical beam instrumentation, including the intra-train luminosity
monitor, must be developed, and an acceptable laser-wire profile monitor
must be provided where needed in each design. A vigorous R&D program
is mandatory for beam instrumentation in general; it would be appropriate
for a collaborative effort between laboratories.
- A
sufficiently detailed prototype of the main linac module (girder or
cryomodule with quadrupole) must be developed to provide information about
on-girder sources of vibration.
- A
detailed evaluation of critical subsystem reliability is needed to
demonstrate that adequate redundancy is provided and that the assumed
failure rate of individual components has been achieved.
- The
performance of beam based tuning procedures to align magnets and
structures must be demonstrated by complete simulations, in the presence
of a wide variety of errors, both in the beam and in the components.
R1
/ R2 Item
|
Person
|
Date
|
1
|
Adolphsen
/ Toge
|
|
2
|
Tantawi
/ Chin
|
|
3
|
Chin
/ Cornuelle
|
|
4
|
Schultz
/ Toge
|
|
5
|
Pivi
/ Yokoya
|
|
6
|
Raubenheimer
/ Yokoya
|
|
7
|
Urakawa
/ Ross
|
|
8
|
Wolski
/ Urakawa
|
|
9
|
Tenenbaum
/ Kubo
|
|
10
|
Ross
/ Hayano
|
|
11
|
Seryi
/ Tauchi
|
|
12
|
Himel
/ Phinney
|
|
13
|
Kubo
/ Tenenbaum
|
|
Overall
Edit
|
Phinney
/ Yokoya
|
|