Minutes of Weekly JLC Physics Group Meeting
-------------------------------------------
Place: 3F Bldg 3, KEK
Time: 10:30, 98/11/06
[0] Agenda
0.1) Miscellaneous Notifications
0.2) CDC R&D Status
[1] Miscellaneous Notifications
[1-1] HP-UX OS Upgrade (A.Miyamoto)
Network security is one of the biggest problems these days.
Since HP-UX 10.10, our current OS for jlcux's, does not allow
shadow passwords under CDE, it is necessary to upgrade to
HP-UX 10.20. The upgrading will be carried out by the end of
this year.
[2] CDC R&D Status (Y.Kato)
Y.Kato from Kinki University reported on the status of wire
tension measurements. He set up a test stand there and started
preliminary measurements in July.
So far 3 measurements have been done:
July 14 --> Sep.19 --> Oct.22
A quick initial tension drop was observed as with the 4.6m
chamber. Since then the tension drop becomes slower but is
still too early to draw any conclusion.
fujiik@jlcux1.kek.jp