			Weekly JLC Physics Group Meeting
			--------------------------------

Place: BLDG 3, KEK
Time:  10:30, 97/01/17

[0] Agenda
   
   0.1) CAL Subgroup Status Report
   0.2) Others
   
   		
[1] CAL Subgroup Status (Y.Fujii)
	
   1.1) Test Calorimeter Construction
   
   	Scintillators	: completed and surveyed
   				2.0 p.e./layer for a beta-source
   	Light guides	: almost ready
   	Lead plates	: surveyed and ready
   	Structure	: test assembling showed 4mm distortion as expected.
   			  ---> needs adjustment
   			
   1.2) Schedule
   
   	Early Feb.	: finish assembly
	Feb.20 - 25	: setup in PS
	Feb.26 -	: beam run 
	Mar.13		: finish beam run
	
	Jun. someday	: 2-nd beam test
			  aims at taking data for Pb/Sci = 4/2, 6/2
			  with additional scintillators.
			  
	Summer		: convert the sci-fi readout scheme to sigma-fiber
			  configuration.   

	Jan. 1998	: 3-rd beam test
	
   1.3) Problem
   
   	Timely delivery of additional scintillators requires purchase order
   	in this fiscal year.
   	
[2] Others

   2.1) JPS 97 Spring Meeting
   
   	Those who wish to participate in the meeting should contact
   	T.Matsui for travel expenses.
   	
   2.2) Kakenhi 96
   
   	Those who are responsible for the manuscripts should respect
   	the dead line for the first draft: Feb. 1
   	
   2.3) eXodus 6.0.1
   
   	eXodus 6.0.1 is now available in room 416.
   	

fujiik@jlcux1.kek.jp